Condon Shell Parking Lot, Bow Street Repaved
|The newly configured 86-space parking lot at Condon Shell is now open for public use. Reconstruction of the parking lot, a new pathway, landscaping, benches, interpretive signage and a canoe launch are the first part of a two part project that also includes building a new band shell that is two and one half times the size of the existing one. According to Community Development Director Lauren DiLorenzo, final construction of the park project will be completed shortly. The project is being funded by a federal grant of $550,000 and a signage grant of $40,000 from the Mass Environmental Trust.
The repaving of Bow Street in South Medford. The project is part of a $1.2 million federally funded contract that included the reconstruction of Bow Street, Kilsyth Road, and Revere Place by contractor Cedrone Trucking of Billerica and paving subcontractor D&R Paving.
– Photos submitted by Lauren DiLorenzo